Morningview drive Eustis House #2

We just bought another piece of land. Waiting on survey.

Working on house design at the moment.

Final design below, submitted for permit yesterday.

Week #1 Update (7/31/2021

Lot has been cleared waiting for stake out.

Week #9 (9/25/2021)

It has been some time since our last update. We found a gopher tortoise burrow in our site and we have to take care if. This process involved a certified agent and permit from the the Florida Fish & Wildlife Conservation Commission.

Anyway, we are back and running.

The lot stake out have been performed by the Surveyors and the digging for the basement have been completed.

Next week we hope to start the basement footings and retention wall.

Week #11 (10/9/2021)

Footings for the 1st floor/Basement walls are poured, waiting for the CMU blocks.

Week 19 - Basement Footings

Week #12 (10/11/2021

Week #13 (11/23/2021)

Week #20 (12/10/2021)

Week #22 (12/23/2021)

Week #24 (01/08/2022)

Week #27 (01/30/2022)

Week #29 (2/13/2022)

Interior framing have been done, HVAC and Electrical started.

3/1/2022

Roof shingles done.

4/1/2022

Stucco have been done, waiting on drywall delivery.

5/18/2022

We have made some progress in the last few weeks. We finally got the drywall, paint, fascia, soffits, garage and entry door, balcony, floors and shower/tub walls

6/4/2022

Driveway done!

7/16/2022

House finished and Listed! Click Here

Brand new construction for sale in Eustis Florida.